Thursday, November 1, 2012

Thursday, November 1, 2012

What is going on this week is either more of the same or is fairly subtle stuff that might be readily obvious.
 
One thing that is obvious is that the building access is being tightened as shown by the wood partitions across the doorways in this picture. Because live electricity is now present and for other reasons, safety is a concern, so access is being restricted.
Electrical conduit is snaking its way all over the building to hook up wall switches and electrical outlets.
Stacks of sheetrock are all over the building. Since the roof is now secure, and the building is pretty well "dried in", the stacks of sheetrock can only mean one thing.......
And that one thing is that solid walls are going up!

 
 
Up on the platform high above the worship space floor, the spraying of the underside of the roof with the black sealer material is near completion.
 
Insulation between the wall studs in the upper level of the worship center is in place. Sheetrock in this area is not far behind!
The white final roofing on the roof over the main lobby is progressing.
You have seen pictures of the brick exterior on the side facing the current sanctuary in previous blogs, but now brick is being laid on the side facing the parking lot. Now you can see in person when you drive in the pakring lot how good this building will look!
 
 
 
 