Details keep filling in!
 
 

The green wall color in this picture in one of the large bathrooms is not paint. It's wall paper. 
 

And still in the bathroom, a not-so-exciting but very necessary detail has been added. Divider partitions are not far behind (no pun intended!).




















Water fountains.
















Wall trim in the upper lobby. The stonework at the base of the columns probably will be added next week.










Beautiful stone wall trim in The Pit (lower level youth assembly room).













A ton of details appearing in the Worship Center. The wall area at the back of the chancel is really filling in and taking form.
 
The choir risers have their superstructure.
 
 
 
 
 
 
 
 
 
 
 
 
 
 
The sheetrock facing has been installed in the balcony.
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
The railings and handrails have been installed in the balcony.
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
The final sections of the wood ceiling will be installed next week. This will fill in the four open sections around the center panels. It's gorgeous now, but the completed ceiling will be awesome!
 
 
 
 
 
 
 
 
 
 
A really nice detail is the installation of the railings along the edge of the Upper Commons (upper lobby) overlooking the Lower Commons.
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
The queen got some royal jewels. The green geometric panels were mounted between the four columns.
 
 
 
 
 
 
 
 
 
 
 
 
 
The parking lot across the street on Mammoth Lakes Drive
now has been totally cleared, and it is apparent how large this lot is. It was a stretch in 2006 to purchase this lot, but hindsight now supports the move totally in view of the need for parking spaces!