Thursday, April 12, 2012




So how far along are we? The foundation trenches for ALL the outside walls have been dug except for a small area. And those final trenches should be done within the next several work days.






And this picture was taken right in front of where the front door will be. The trench with the green vertical arrows is the location of the front wall of the building. That concrete wall at the back of the picture looks a l-o-n-g ways away!







The foundation walls inside the red boxes already have been formed. The walls inside the green boxes are scheduled for a concrete pour on Thursday afternoon, April 12.








And for the youth of our church.....

Hopefully you have heard about the youth assembly room and classrooms in the lower level of the building. In this picture, the foundation trenches for the youth assembly room are outlined in red.





By this same time next week when the next update appears, there will be a LARGE crane on the construction site, and that will be followed by the delivery of steel beams. If you thought things were starting to get interesting, just wait until the steel superstructure starts going up!